Microsoft has signed a five-year, $9.7 billion contract with Australian data-center operator IREN to secure access to Nvidia's next-gen GB300 accelerators and associated infrastructure at IREN's Texas campus. The agreement effectively lets Microsoft rent future GPU capacity in bulk rather than owning all of the hardware and power footprint itself, using IREN's balance sheet and Dell-supplied equipment as an intermediary.
According to public filings and press reports, Microsoft is committing roughly $9.7 billion over five years for cloud services built on accelerator systems using Nvidia GB300 parts. IREN, in turn, is signing a separate $5.8 billion agreement with Dell to procure the Nvidia-based systems and data-center hardware for deployment at its Childress, Texas site. The campus is being expanded towards a 750 MW power envelope, with about 200 MW of "critical IT" capacity earmarked for Microsoft's workloads in the first phase.
Microsoft will make a significant upfront payment to IREN, which helps fund the capex. In exchange, it gets contracted access to GB300-class capacity without having to build and own the entire site. The arrangement is contingent on IREN meeting construction and delivery milestones; if those slip, the effective capacity Microsoft gets could be delayed.
Microsoft has been frank that its AI infrastructure is supply-constrained and likely will be into mid-2026. Nvidia's top-end accelerators are still bottlenecked by advanced packaging, HBM, and foundry limits. Hyperscalers with the deepest pockets are effectively queuing up capacity years in advance. This deal is Microsoft paying to reserve a slice of that future GB300 pipeline.
There are also balance-sheet reasons. Building and owning every megawatt of AI data-center capacity ties up capital in facilities that age quickly as each GPU generation arrives. By leaning on specialist operators like IREN, Microsoft can push some of the heavy construction and power-infrastructure risk off its own books. It still commits the spend, but through service contracts that can be accounted for differently from pure capex on land and buildings.
IREN's core pitch is renewable-powered, large-scale data centers. Historically, it has had roots in energy-intensive businesses such as Bitcoin mining; AI gives it a higher-margin outlet for those power assets.
On paper, Microsoft could buy GB300 systems directly from Dell and drop them into Azure regions it owns. Using a partner instead suggests a mix of speed, power access, and risk-sharing considerations:
The IREN deal slots into a wider pattern: hyperscalers tying up multi-year supply commitments for premium accelerators while pushing part of the physical infrastructure burden downstream. The interesting point here is the scale and specificity -- this is not generic cloud capacity, but explicitly Nvidia GB300-based systems.
For the rest of the market, the message is blunt: if you are not pre-paying for Nvidia capacity or building around alternative silicon (AMD, Intel, in-house accelerators), you will compete for leftovers. Even well-funded AI startups may find themselves priced out of first-wave GB300 deployments.
This is less about some new strategic epiphany and more about execution at scale. Everyone wants Nvidia's next generation; only a handful of players can pre-commit billions, secure the power, and still sleep at night. Microsoft is simply codifying that reality into long-dated contracts and letting specialist operators carry more of the construction risk.